Facility profile California
Project 14:14 Inc
Project 14:14 Inc is a program in Fresno, California.
Licensing and inspections
- License category
- Short Term Residential Therapeutic Program (STRTP)
- Executive director
- RITA STEVENSON
- Licensed capacity
- 6
34 inspection reports on file. Search all California reports
The newest 25 reports, by date: 10 findings in 10 reports
- Sep 18, 2026 Complaint Investigation - Unsubstantiated - 1 allegation
-
Aug 12, 2026
Complaint Investigation - Unsubstantiated - 1 allegation
1 finding
-
Substantiated
On August 12, 2026 , Licensing Program Analyst (LPA), Melissa Renovato conducted an unannounced visit to the Project 14: STRTP in order to deliver the findings of the above allegation and met Chasity Day, Director. On June 22, 2026, the above allegation was referred to Community Care Licensing for investigation. The investigation included an inspection of the Facility, confidential interviews, and review of records. Based on the information obtained, there is a preponderance of the evidence to prove the above allegation occurred therefore this allegation is Substantiated. The Facility was cited for ILS, Version 5, Section Personal Rights. See LIC9099D. Plans of Corrections were reviewed and developed with Chasity Day. A copy of this report and appeal rights were provided at the conclusion of the inspection.
-
- Aug 12, 2026 Complaint Investigation - Unsubstantiated - 1 allegation
- Aug 12, 2026 Complaint Investigation - Unsubstantiated - 1 allegation
- Jul 30, 2026 Facility Evaluation
- Jul 13, 2026 Complaint Investigation - Unsubstantiated
-
Jul 13, 2026
Facility Evaluation
1 finding
-
Deficiency cited at inspection
On June 25, 2026, Licensing Program Analyst (LPA) Miriam Flores conducted a Case Management inspection at Project 14:14 and met with Direct Care Staff, Aiyana Cain. Administrator, Rita Stevenson participated on this inspection via phone. The purpose of the inspection was to follow up on two incident reports. Incident reports are both dated 6/22/26. Staff (S1) administered over the counter medication to C1 without medical clearance. Incident reports are both dated 6/22/26 and were sent late to CCL on 7/01/26 by S2. The Department determined this to be an immediate risk to health and safety at this time. The facility is cited on the attached LIC809D for 80075(D) Health Related Services and 80061(b) Reporting Requirements. An exit interview was conducted and a copy of the report and appeal rights were provided to the facility.
-
- Jun 25, 2026 Complaint Investigation - Unsubstantiated
-
Jun 25, 2026
Facility Evaluation
1 finding
-
Deficiency cited at inspection
On June 25, 2026, Licensing Program Analyst (LPA) Miriam Flores conducted a Case Management inspection at Project 14:14 and met with Facility Manager, Sophia Alvarez. The purpose of the inspection was to discuss the facility emergency food supply. During facility inspection, facility failed to maintain the required emergency food supply. At the time of the inspection, the facility did not have a minimum one-week supply of staple non perishable foods. The Department determined this to be an immediate risk to health and safety at this time, therefore Interim Licensing Standards (ILS) Food Services 87076(c)(1) are being cited on the attached LIC809D. An exit interview was conducted and a copy of the report and appeal rights were provided to the facility.
-
-
Jun 19, 2026
Complaint Investigation - Substantiated - 1 allegation
1 finding
-
Substantiated : 87061(b)
On June 19, Licensing Program Analysts (LPAs) Miriam Flores and Arisveh Cervantes conducted a complaint inspection at Project 14:14 and met with Chief Executive Officer, Chasity Day and Facility Manager, Sophia Alvarez. The purpose of the inspection was to deliver the findings for the above complaint allegations. During the course of the investigation, Community Care Licensing (CCL) conducted confidential interviews and reviewed supportive documentation which revealed that facility did not meet reporting requirements for the authorized representative. Based on the information obtained, the preponderance of evidence standard has been met, therefore the above allegation is found to be SUBSTANTIATED. California Code of Regulations are being cited on the attached LIC 9099D. Facility was cited for The Interim Licensing Standard (ILS) Chapter 7. Version 3. Articles 1 through 10. The Agency is being cited for violations of Section 87061(b) Reporting Requirements.
-
- Jun 8, 2026 Facility Evaluation
-
Jun 2, 2026
Facility Evaluation
1 finding
-
Deficiency cited at inspection
On the above date, Licensing Program Analyst (LPAs), Melissa Renovato and Jennie Estrada arrived at Project 14:14 in Fresno, CA for the purpose of conducting an unannounced Case Management inspection and met with Sophia Alvarez, Facility Manager. The purpose of the inspection was to discuss reporting responsibilities. On March 26, 2026, Community Care Licensing (CCL) received a 24 hour incident notification for an incident that occurred on March 21, 2026 involving law enforcement. CCL received another 24 hour incident notification for the same incident again on March 31, 2026. These initial reports were late and CCL has not received the final report LIC 624LE for this incident. The Department determined this to be a potential risk to health and safety of the children in care at this time, therefore ILS for STRTP, Version 5, Section 87061(j)(1) Reporting Requirements is being cited on the attached LIC809D. An exit interview was conducted, and a copy of the report and appeal rights were provided at the conclusion of the inspection.
-
-
Apr 30, 2026
Facility Evaluation
1 finding
-
Deficiency cited at inspection
On April 30, Licensing Program Analyst (LPA) Miriam Flores traveled to Project 14: Inc in Fresno, CA to conduct an unannounced inspection for the purpose to complete an Annual/Required inspection. LPA met with Administrator, Rita Stevenson. A review of the Licensing Information System is dated 4/28/26 indicates that all facility staff are associated to this STRTP had DOJ, FBI, and child abuse index check clearances. Five staff files were reviewed during this inspection. The following was observed during the facility inspection: At 09: AM LPA reviewed the Disaster Preparedness Plan At 10: AM LPA conducted file review for staff. At 12: PM LPA conducted confidential staff interviews. Three deficiencies are being cited on the following sections Emergency Intervention Staff Training 8795.65(e); Supervision Evaluation and Training Requirements 87065.1(e)(1) and Personnel Records 80066(a)(10) based on record review in accordance with the California Code of Regulations, Title 22. The facility is being cited on the attached LIC 809D. Exit interview was conducted and a copy of this report and appeal rights was left at agency with the Administrator.
-
- Apr 28, 2026 Facility Evaluation
- Jan 8, 2026 Facility Evaluation
- Dec 3, 2025 Facility Evaluation
- Oct 6, 2025 Facility Evaluation
- Jul 23, 2025 Facility Evaluation
- Jul 23, 2025 Facility Evaluation
-
Jun 3, 2025
Complaint Investigation - Unsubstantiated - 1 allegation
1 finding
-
Substantiated
On June 3, 2025, Licensing Program Analysts (LPAs) Briana Placencia and Angelica Borja conducted a complaint inspection at Project 14: STRTP, LPAs met with Camia Scherer. The purpose of the inspection was to deliver the findings for the above complaint allegation. During the investigation, LPA interviewed staff and clients which revealed that in fact facility staff were searching rooms. Based on LPA's observations, and interviews which were conducted, the preponderance of evidence standard has been met, therefore the above allegation is found to be SUBSTANTIATED. An exit interview was conducted, and a copy of the report and appeal rights were provided to the facility.
-
-
Jun 3, 2025
Facility Evaluation
1 finding
-
Deficiency cited at inspection
On June 3, 2025, Licensing Program Analysts (LPAs) Briana Placencia and Angelica Borja conducted a Case Management inspection at Project 14: STRTP and met with Camia Scherer and Rita Stevenson via phone. The purpose of this visit was to discuss incident reports not received by Community Care Licensing (CCL). During a previous investigation it was discovered that incidents occurred with Client One (C1- See 811 for confidential names) on March 6, 2025 and March 8, 2025. Both these incident reports were not received by CCL. The Department determined this to be a risk to the health and safety of the children in care at this time, therefore California Code of Regulations are being cited on the attached LIC809D. A copy of this report and Appeal Rights was provided to the facility.
-
-
Jun 3, 2025
Complaint Investigation - Unsubstantiated - 1 allegation
1 finding
-
Substantiated
On June 3, 2025, Licensing Program Analysts (LPAs) Briana Placencia and Angelica Borja conducted a complaint inspection at Project 14: STRTP, LPAs met with Camia Scherer. The purpose of the inspection was to deliver the findings for the above complaint allegation. During the investigation, LPA interviewed staff and clients which revealed that in fact facility staff were searching rooms. Based on LPA's observations, and interviews which were conducted, the preponderance of evidence standard has been met, therefore the above allegation is found to be SUBSTANTIATED. An exit interview was conducted, and a copy of the report and appeal rights were provided to the facility.
-
- May 12, 2025 Facility Evaluation
- May 12, 2025 Facility Evaluation
-
Apr 16, 2025
Facility Evaluation - 3 deficiencies
1 finding
-
Deficiency cited at inspection
On April 16, 2025, Licensing Program Analysts (LPAs) Briana Placencia and Melissa Renovato conducted an unannounced Annual/Required inspection at Project 14:14, located in Fresno CA. LPAs met with Administrator Rita Stevenson. A physical plant inspection was completed and included the following checks. Adequate indoor and outdoor activity space and materials observed. The facility is maintained at 72 degrees. All facility smoke detectors are in appropriate working order. Facility maintains an adequate supply of perishable and non-perishable foods. All required forms are posted. Medications are locked and centrally stored. Individual beds were observed. STRTP was approved on April 15, 2024. The licensee has submitted their required documentation to obtain their Mental Health Approval, at this time it is pending. The facility is working on being accredited through CARF. Project 14:14 is currently on a provisional license that expired on 4/15/2025. Project 14:14 will have their provisional license extended for another 6 months. Per Administrator there are no weapons/firearms in the facility. There are no bodies of water. LPAs reviewed 3 client files, and 5 staff files. LPAs interviewed 1 staff and 2 clients. The facility is being cited on the attached LIC D's. A copy of this report and appeal rights was left with Administrator Rita Stevenson at the conclusion of today's inspection.
-
We have questions about Project 14:14 Inc
If you were there, worked there or sent your child there, you can help fill in what our records are missing. Each question takes a moment; skip anything you do not know.